You can build a guest house in Benton or Washington County, but the rules depend on whether your land sits inside a city or out in the county. In unincorporated Washington County, a second home generally needs at least 2 acres, and in unincorporated Benton County a guest house needs a building permit because it has living space.
A lot of land in our two counties is not inside any city, and the state law that gets the most attention for guest houses speaks to cities and towns. This guide sorts out which rules apply where, what each county puts in writing and what to confirm before you pay for plans.
City Limits or County Land: Start Here
Before anything else, find out who has authority over your parcel. Inside a city or town, the city’s planning department handles zoning, and Arkansas Act 313 of 2025 requires cities and towns to allow at least one accessory dwelling unit on a lot with a single-family house. That law sets a size cap of 75 percent of the main house or 1,000 square feet, whichever is less.
Outside city limits, Act 313 does not apply, and the county’s own rules take over. That is the situation for many acreage owners, and it is where most of the confusion starts. If you are not sure which side of the line you are on, the county planning office can tell you from the parcel number. If your parcel is inside a city, start with that city’s planning department, because this post stays on county land.
What Washington County Requires for a Second Home
Washington County’s Planning Office publishes an Additional Dwelling Unit checklist and application, and it is the clearest written answer we found. According to the county’s ADU checklist and application, a guest house counts as another single-family home on the property, and it has to meet the conditions below.
| Condition | What the county asks |
|---|---|
| Acreage for two homes | At least 2 acres |
| Acreage for three homes | At least 3 acres |
| Access | Road frontage on a public road or a 30-foot access and utility easement to one |
| Water | A water tap, or room for a well alongside both septic systems |
| Septic | Capacity confirmed by the Health Department, or a separate septic design |
| Septic timing | Installed and operational before the new home is occupied |
| Front setback | 25 feet from the property line and road right-of-way |
| Side setback | 10 feet from each side property line |
| Rear setback | 20 feet from the rear property line |
| Space between buildings | At least 20 feet between structures |
| Easements | The new home cannot encroach on utility or other easements |
The application also asks for a concept or sketch plan that shows the existing house and the proposed guest house along with the driveway, and the owner signs it under penalty of perjury. If your subdivision has stricter setbacks, the stricter ones apply. The county says it does not regulate or enforce private covenants or deed restrictions, so an HOA or deed restriction can still stop a guest house that the county would approve.
A second or third residence goes through an administrative process with the Planning Office. County planning guidance says four or more residences may need review by the Planning Board, so a guest house on its own should not reach that level.
The 2 Acre Test Is About the Parcel, Not the Yard

Owners often count the mowed area around the house and decide they are short on land. The county looks at the parcel, so the number that matters is the acreage on the deed or the county record. A 2.1 acre parcel that is mostly wooded slope still passes the acreage test, though it may fail the practical one.
The acreage number also moves in one area. The checklist says parcels inside the City of Goshen’s planning area need 4 acres for two homes and 6 acres for three, because the minimum density there is one unit per two acres. If your land is near Goshen, ask the Planning Office which minimum applies before you assume 2 acres.
The practical test is where the other conditions bite. A 20 foot gap between buildings and every property line setback eat into the buildable area, and an existing well and septic field take up more. Before you commit to a site next to the main house, draw the setbacks on a parcel map and see what is left.
Do You Need a Building Permit? The Two Counties Differ
This is the question owners ask first, and the two counties answer it differently.
In unincorporated Benton County, the county’s Building Safety Department requires a building permit for new construction of a single-family home, and separate trade permits for new wiring and for plumbing or HVAC work. A November 2023 change exempts detached buildings with no living space, such as shops and storage buildings. A guest house has living space, so it does not fall under that exemption. New driveways need a separate permit from the Benton County Road Department.
Washington County works differently. The county’s planning guide for people building a residence says the county does not require traditional building permits for single-family homes or personal accessory buildings, though state code still applies. That does not mean there is nothing to file. The county lists a floodplain development permit for mapped flood zones and a Health Department permit for septic. A driveway permit may also apply where you connect to a county road or state highway. The county’s applications page points the same way. It lists an ADU application that is sent with the 911 address application, along with a floodplain permit application and an Arkansas Fire Prevention Code acknowledgement form, and it lists no building permit application. Plan on paperwork even without a building permit.
| Topic | Unincorporated Benton County | Unincorporated Washington County |
|---|---|---|
| Building permit for a guest house | Yes, through Building Safety | Not a traditional building permit, per the county planning guide |
| Detached shop or storage building | Exempt since November 2023 | Not required, per the county planning guide |
| Second dwelling approval | Ask the planning office, since no approval steps are published | ADU checklist and application |
| Driveway | Road Department permit for a new driveway | Driveway permit where it meets a county or state road |
Benton County: What the County Publishes and What to Ask
Single-family residential and agricultural use is allowed by right on unincorporated Benton County land, so one house on a parcel does not need Planning Board approval or rezoning. The county FAQ is clear that this does not mean permits are optional, and setbacks and easements still apply along with density limits.
Benton County’s Planning and Development Regulations do recognize second homes. They define an accessory dwelling unit as a secondary home on the same lot as a primary dwelling that can be lived in on its own, and they say it shall not exceed 50 percent of the primary home’s habitable space. What we could not find is a section that sets an acreage minimum or spells out approval steps for one on a rural lot, and the county planning FAQ does not mention guest houses either. Call the Benton County planning office and ask whether a second dwelling is allowed on your parcel, whether there is a minimum acreage and what setbacks apply. Get the answer in writing before you hire a designer. Our barndominium permits and zoning county guide walks through how the Benton County residential submission works, and a guest house follows the same path.
Septic and Wells Decide More Projects Than Zoning Does
On acreage, the septic system is usually the item that shapes the project. Washington County planning guidance says each residence needs its own septic system, and the ADU checklist says a Health Department designee must confirm that the existing system has capacity or that a separate design is needed. Both point the same way. Plan on a second system unless the Health Department tells you the first one can carry both homes.
If you use a well, the county guidance says septic systems must sit at least 100 feet from it. On a tight site, that single distance can decide where the guest house goes. In Benton County, the Arkansas Department of Health handles septic and well permits, and the same state rule applies in both counties: a permit is required before an onsite wastewater system is built or changed. It is a separate process from the building permit.
Start the soil test early. A perc test takes time to schedule, and its result can move the guest house from the spot you wanted to the only spot that works.
Other Details That Hold Up a Move-In
Zoning and septic get the attention, but a few smaller items can delay a project. Washington County requires each residence to have its own 911 address, and the ADU application is sent in together with the 911 address application, so file the two as a pair. Structures cannot sit in the road right-of-way, and the county does not allow backing onto county roads, so the driveway layout deserves a look before the pad is cut. Utility providers may also have their own permit and inspection steps.
City vs. County: How the Rules Compare
The table below puts the three situations side by side so you can see what changes when the property line moves.
| Topic | Inside a city or town | Unincorporated Washington County | Unincorporated Benton County |
|---|---|---|---|
| Who sets the rules | The city planning department | The county Planning Office | The county planning and Building Safety offices |
| Second home allowed | Yes, one unit by right under Act 313 | Yes, with 2 acres for two homes | Recognized in the regulations, but confirm acreage and approval with the county |
| Size cap | 75 percent of the main house or 1,000 square feet | Not stated in the checklist | 50 percent of the main home’s habitable space, per the county’s ADU definition |
| Septic | Depends on sewer access | Health Department review, own system unless capacity is confirmed | Arkansas Department of Health permit |
An Order of Operations That Saves Money
The order you do things in matters as much as the rules themselves. Delays usually come from designing first and checking constraints second. This sequence avoids that.
| Step | What to do | Why this order |
|---|---|---|
| 1 | Confirm whether the parcel is in a city or the county | It decides which rules apply |
| 2 | Pull the parcel acreage and any covenants | Acreage and deed limits can end the project |
| 3 | Call the county planning office | Written answers beat assumptions |
| 4 | Schedule the soil test and septic review | Septic placement shapes the site plan |
| 5 | Draw setbacks and the 20 foot gap on a parcel map | It shows the real buildable area |
| 6 | Design and price the guest house | Now the plan fits the site |
Frequently Asked Questions
How many acres do I need for a guest house in Washington County?
At least 2 acres for two homes on the parcel, and at least 3 acres for three homes, according to the county’s ADU checklist. Parcels inside the City of Goshen’s planning area need 4 and 6 acres.
Does Act 313 apply to land outside city limits?
No. The act requires cities and towns to allow an accessory dwelling unit, so unincorporated land follows county rules instead.
Does a guest house need its own septic system?
Plan on it. Washington County guidance says each residence needs its own system, and the Health Department decides whether an existing system has the capacity to carry a second home.
Do I need a building permit for a guest house in Benton County?
Yes. Benton County requires a building permit for new single-family construction, and the exemption for detached buildings covers only structures with no living space. New wiring needs its own trade permit, as do plumbing and HVAC work, and septic is permitted separately through the Arkansas Department of Health.
Do I need a building permit for a guest house in Washington County?
The county planning guide says Washington County does not require traditional building permits for single-family homes, though state code still applies. You still need the county’s ADU approval and a septic permit, plus any floodplain or driveway permits that fit your site, so confirm the full list with the Planning Office.
Can a homeowners association or covenant stop my guest house?
Yes. Washington County does not enforce private covenants or deed restrictions, so you are responsible for checking them even when the county approves the project.
Planning a Guest House in Benton or Washington County Starts With the Parcel
Building a guest house in Benton or Washington County comes down to the parcel. Check whether you are in a city or the county. Then confirm acreage and covenants, and settle the septic plan before you design anything. In Washington County, a second home needs at least 2 acres, and in Benton County you should get the second dwelling answer in writing along with the building permit requirements.
If you want a custom builder in Northwest Arkansas to look at your parcel before you commit to a plan, or you need help with guest house construction in Northwest Arkansas, contact Torres Construction Group and we will walk the site with you.